Hays County is advancing multimodal improvements to enhance connectivity, safety, and accessibility between Wimberley Square, Blue Hole Park and adjacent trail segments.
Initial concepts for roadway improvements were first identified in the Wimberley Valley Trails Master Plan, completed in 2022, by Hays County in partnership with the Cities of Wimberley and Woodcreek. The plan established a multi-year vision for hike-and-bike trails, sidewalks and other transportation and mobility improvements throughout Wimberley and Woodcreek.
COST: $2.7M
HAYS CO. CERTIFICATES OF OBLIGATION
COST: $3.3M
CAMPO CARBON REDUCTION PROGRAM

IMPROVEMENTS
-
Convert the roadway to one-way travel
-
Add a dedicated bike lane separated from the travel lane by
a median -
Install sidewalks on both sides of the roadway
-
Construct a roundabout at the intersection of Blue Hole Lane
ANTICIPATED SCHEDULE
Design
ROW Acquisition
Utility Coordination
Construction
Mid 2026 to Early 2028
Mid 2026 to Late 2027
Mid 2026 to Mid 2028
Late 2028 to Mid 2030
RIGHT OF WAY
Additional ROW will be needed to construct the multi-modal improvements. Hays County will coordinate with affected property owners to acquire the necessary ROW.