Hays County aims to enhance east-west mobility, improve safety, and reduce congestion by advancing plans to extend William Pettus Road. The proposed roadway connection is intended to help manage traffic in one of Central Texas's fastest-growing areas, including San Marcos and Kyle.
The extension of William Pettus Road from FM 110 to SH 21 was identified as a key priority in the CAMPO’s 2019 Western Caldwell County Transportation Study. This effort is being coordinated with Caldwell County’s project to improve William Pettus Road from SH 21 to SH 142.
This project will include design, right-of-way (ROW) acquisition, and utility coordination. Construction is not currently funded.
COST: $3.7M

IMPROVEMENTS
Extend William Pettus Road to include:
-
One travel lane in each direction with a center turn lane
-
Shoulders on both sides of the road
ANTICIPATED SCHEDULE
Design
ROW Acquisition
Utility Coordination
Construction
Mid 2026 - Mid 2027
Mid 2026 - Early 2028
Mid 2026 - Late 2028
Not Funded
RIGHT OF WAY
Because the roadway will follow a new alignment, this project will require additional ROW to construct improvements. As design progresses, a better estimate of ROW needs will be determined.