Hays County, in partnership with the City of Uhland, is designing improvements to reconstruct the existing roadways and add shoulders to improve safety.
The existing road conditions include one lane in each direction with no shoulders. This area continues to grow, and improvements to these roadways are needed to keep traffic flowing safely.
This project will include design, right-of-way (ROW) acquisition if needed, and utility coordination. Construction is not currently funded.
COST: $6.1M

IMPROVEMENTS
Widen the existing roadway to include:
-
Reconstructed travel lane in each direction (no median)
-
Shoulders on both sides of the road
ANTICIPATED SCHEDULE
Design
ROW & Utility Coordination
Construction
Late 2025 - Late 2026
Late 2026 - Early 2028
Not Funded
RIGHT OF WAY
The county will work to make improvements in existing ROW, but additional ROW may be needed to construct these improvements. As design progresses, a better estimate of ROW needs will be determined.