The purpose of this project is to improve pavement conditions and enhance safety. Existing road conditions include one lane in each direction with deteriorating pavement and no shoulders. This area continues to grow, and improvements are needed to keep traffic flowing safely.
This project will include design and right-of-way (ROW) acquisition. Utility coordination and construction are not currently funded.
COST: $1.0M

IMPROVEMENTS
Widen the existing roadway to include:
-
Reconstructed travel lane in each direction (no median)
-
Shoulders on both sides of the road
ANTICIPATED SCHEDULE
Design
ROW Acquisition
Utility Coordination
Construction
Late 2025 - Late 2027
Late 2026 - Mid 2028
Not Funded
Not Funded
RIGHT OF WAY
Additional ROW will be needed to expand the roadway. As design progresses, the county will begin coordinating with property owners.