This project will widen the existing two-lane road to a four-lane divided roadway with a center turn lane. Currently, the road has one lane in each direction and lacks shoulders and turn lanes. The corridor is developed with multiple driveways and turnoffs from High Road. The additional lanes and center turn lane will improve safe, efficient traffic flow.
This project will include design, right-of-way (ROW) acquisition, and utility coordination. Construction is not currently funded.
COST: $8.4M

IMPROVEMENTS
Widen the existing roadway to include:
-
Two lanes in each direction
-
A center turn lane
-
Shoulders on both sides of the road
ANTICIPATED SCHEDULE
Design
ROW Acquisition
Utility Coordination
Construction
2026 – 2027
2027
2027 - 2028
Not Funded
RIGHT OF WAY
Additional ROW will be needed to expand the roadway. As design progresses, the county will begin coordinating with property owners.