Sawyer Ranch Road Widening and Pedestrian Walkway

US 290 to Darden Hill Road

Commissioner Smith, Precinct 4

Hays County is advancing improvements to Sawyer Ranch Road to enhance safety and mobility for drivers, pedestrians, and bicyclists in a rapidly growing area.This area has experienced significant growth, including new and expanding residential developments and new schools. The existing roadway includes one lane in each direction with narrow shoulders.

Sawyer Ranch Road Pedestrian Walkway

Sawyer-Ranch-Road-Pedestrian-Walkway-Map.jpg
PEDESTRIAN WALKWAY COST: $3.4M

The Sawyer Ranch Road Pedestrian Walkway project extends the existing pedestrian walkway from Meadow Creek Drive to Darden Hill Road. Design, utility coordination, and construction are funded for the pedestrian walkway. The existing walkway currently runs from Belterra Drive to Meadow Creek Drive.

IMPROVEMENTS
  • Extend the 10-foot pedestrian walkway along the east side of the roadway from Meadow Creek Drive to Darden Hill Road

  • Add striped crosswalks at key intersections

ANTICIPATED SCHEDULE

Design

Utility Coordination

Construction

Early 2026 - Early 2027

Mid 2026 - Late 2027

Late 2027 - Late 2028

Sawyer Ranch Road Widening Project

Sawyer-Ranch-Road-Widening-Project-Map.jpg
WIDENING DESIGN COST: $1.4M

The Sawyer Ranch Road Widening project will widen the road to two lanes in each direction from US 290 to Darden Hill Road. Currently only preliminary design is funded for the widening project.

IMPROVEMENTS
  • Widen to two lanes in each direction with a grass median

  • The road will be widened to the west to preserve the existing shared use path

  • Add curbs and gutters

  • Smoothing the curve to the South of Rugged Earth Drive

  • Add roundabouts at 

    • Cool Spring Way

    • Rachels Canyon Drive

    • Sycamore Springs Middle School

  • Add signal to intersection at Belterra Drive

  • Improve intersection at US 290

  • Speed Limit to remain 35 mph

ANTICIPATED SCHEDULE

Preliminary Design

Final Design, Utility Coordination,
ROW Acquisition, & Construction

Projected Construction
Completion (if funded)

Early 2026 - Late 2026


Not Funded​

 

2033

OPEN HOUSE
Sawyer Ranch Road Improvements Open House

The Sawyer Ranch Road Open House was held on Tuesday, October 20, 2026, from 5:30 – 7:30 PM at Sycamore Springs Middle School at 4451 Sawyer Ranch Rd, Austin, TX 78737.

​

Community members were invited to attend the open house at their convenience to review exhibits, maps, and project materials and speak directly with members of the project team. Those who were unable to attend in person could review the meeting materials and submit comments from Oct. 20 through Nov. 4, 2026.  