FM 2001 East Interim

Graef Road to southeast of SH 21

Commissioner Ingalsbe, Precinct 1
FM 2001 East Interim Map_20260205.png

Hays County, in coordination with the Texas Department of Transportation (TxDOT), is planning a new alignment of FM 2001 to enhance safety and connectivity in this rapidly growing area. 

​

The County and TxDOT have worked together to identify, design, and construct improvements along several segments of FM 2001. In 2020, TxDOT completed the schematic design and environmental assessment for a new alignment of FM 2001 from I-35 to SH 21. This section of the roadway would ultimately consist of two lanes in each direction, divided by a median, and sidewalks on both sides. These long-term improvements are intended to support future transportation needs and would only be constructed as growth necessitates and funding becomes available. 

​

The current phase of the project focuses on completing design plans to address existing transportation needs by constructing one lane in each direction separated by a median. Coordination with property owners and utility providers is also included in this phase of the project. Construction is not currently funded.

 COST: $1.7M
large-fm 2001 typical section.png
IMPROVEMENTS

Construct a new alignment of FM 2001 to include:

  • One travel lane in each direction separated by a median

  • Shoulders on both sides of the road

  • Turn lanes at intersections

2020 - Late 2026

2020 - Mid 2026

2020 - Late 2026

Not Funded

ANTICIPATED SCHEDULE

Design

ROW Acquisition

Utility Coordination

Construction

RIGHT OF WAY

Because the roadway will follow a new alignment, this project will require additional ROW to construct improvements. ROW acquisition is underway. 